NEW QUESTION # 13
You have a product that can be manufactured on two different production lines in the same warehouse. You create resources and then create individual input locations for the resources. You create two routes. Each route uses different resources.
Materials are staged for consumption in different locations based on the resources being utilized for production.
You need to set up the formula to consume the goods from the correct line-side location.
What should you do?
- A. Select the plan group and consumption operation for each line.
- B. Select resource consumption and the operation for each line.
- C. Select a warehouse and consumption operation for each line.
- D. Specify a site in the formula header.
Answer: B
Explanation:
Section: Create and manage production and lean orders
NEW QUESTION # 14
You are the product manager at a distribution company. You are responsible for managing product compliance standards and reporting.
Chemical product, C00D1 can be sold in all parts of the United States except for the state of California.
You need to set up these compliance requirements for C0001.
Which four actions should be performed in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Answer:
Explanation:
1 - Open the Restricted products regional lists form.
2 - Create an inclusive list type for the United States.
3 - Create an exclusive list type for California, United States.
4 - Add item C0001 to the restricted product lists.
Reference:
https://docs.microsoft.com/en-us/dynamicsax-2012//restricted-products-item-by-country-or-state-form?redirectedfrom=MSDN
NEW QUESTION # 15
A company makes engine parts used in the automotive industry.
They are in the process of retooling an existing manufacturing plant. They are looking to use Dynamics 365 for Finance and Operations to help support the Bill of Materials (BOM) product lifecycle for engineering version control.
You must translate existing production processes into the proper elements. You need to create BOM lifecycle states to translate existing production processes into the proper elements.
What type of BOM product lifecycle state should you create? To answer, select the appropriate BOM state in the answer area.
Answer:
Explanation:
Explanation
NEW QUESTION # 16
Note: This question is part of series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A manufacturing plant uses batch tracking of raw materials, semi-finished goods, and finished goods.
It is difficult to determine when semi-finished and finished goods were produced and expired.
You need to incorporate automatic batch expiration dates for tracked items that are produced.
Solution:
1. Assign shelf life period in days to the items that require expiration dates.
2. Create a new batch number in the tracking dimensions for the items.
3. Enter the manufacturing date.
4. Save the record.
Does the solution meet the goal?
- A. No
- B. Yes
Answer: B
NEW QUESTION # 17
A manufacturing company is implementing Dynamics 365 for Finance and Operations. The company uses a standard costing model to value inventory.
During the setup of the system, all areas that impact the standard cost of the item must be configured correctly to calculate a complete standard cost by using routing, Bill of materials (BOM) and overhead burden.
You need to verify that all areas of the system are correctly configured.
Which object does NOT impact the standard cost of manufactured items?
- A. cost categories
- B. item group
- C. BOM formula
- D. cost groups
Answer: C
Explanation:
Section: Set up and configure manufacturing
Explanation/Reference:
NEW QUESTION # 18
You are a manufacturing consultant helping a client test out different bill of material (BOM) and route consumption options when starting production orders. Material and labor consumption are to be completed before Report as finish.
You are running a production order with BOM lines that have a Flushing principle set to Start. The Automatic Route Consumption Runtime has been set to Yes.
You have set up the default Start user options for all production orders as shown in the exhibit below.

Answer:
Explanation:

NEW QUESTION # 19
You are the production planner for a manufacturing company.
After running operations scheduling for a production order, the following error message displays:
You need to identify the cause of the error.
Which two actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
- A. Review the calendar for the resource to determine if it is expired.
- B. Review the resource group assigned to Operation 10. Check to see if there is a calendar assigned and if the calendar is expired.
- C. Navigate to the work calendar and view working times. Validate that there are working days created in the scheduled period.
- D. Review the available resources for Operation 10. Navigate to the Resource form and validate whether there is a calendar assigned.
Answer: A,D
Explanation:
Section: Create and manage production and lean orders
NEW QUESTION # 20
A company wants to account for the time to set up a machine to manufacture a new part.
You need to set up the costing calculations in the system.
Which three calculation group warnings can you set up? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
- A. No cost price
- B. No resources
- C. No BOM
- D. No route
- E. No consumption
Answer: A,C,D
Explanation:
Reference:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/cost-management/bom-calculation-groups
NEW QUESTION # 21
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some questions sets might have more than one correct solutions, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A manufacturing plant uses Lean process. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service.
You need to create a subcontracting activity for the painting service.
Solution:
1.) Create a purchase agreement for the subcontracting vendor that contains the pricing information for SP-01
2.) Create a vendor resource and a work cell for outsourced painting, then add the resource to the work cell
3.) Create a production flow process activity using the painting work cell and the service item as the picking activity
4.) Create a service term on the activity to tie the purchase agreement to the activity Does this solution meet the goal?
- A. No
- B. Yes
Answer: B
Explanation:
Explanation/Reference:
References:
https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/production-control/activity- based-subcontracting
NEW QUESTION # 22
A company produces light projection toys for holiday decorations. The company plans to implement Lean manufacturing processes.
Production master data must meet the following requirements:
Visual templates for a holiday must only be included for in-store products where that holiday is celebrated Visual templates for a holiday must only be included for in-store products based upon that season Online customers must be able to order visual templates for any holiday or region.
You need to implement production master data.
What should you configure? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
Answer:
Explanation:
NEW QUESTION # 23
You need to determine the sales price for a new limited-edition bicycle for the summer season.
What should you do?
- A. Create the production order for the limited-edition bicycle and click estimate.
- B. Run inventory close for the BOM items for the limited-edition bicycle.
- C. Run the category price rules for the limited-edition bicycle using a cost-plus calculation.
- D. Run the pricing simulator for the limited-edition bicycle for a quantity of one.
Answer: A
NEW QUESTION # 24
You need to configure costing for raw materials used to manufacture unscented cleaning solution.
Which form should you use?
- A. Pricing calculation
- B. Cost basis type
- C. Quantity and margin template
- D. Pricing template
Answer: C
Explanation:
Reference:
https://docs.microsoft.com/en-us/dynamicsax-2012//quantity-and-margin-template-form?
redirectedfrom=MSDN
NEW QUESTION # 25
A pharmaceutical manufacturer uses Process manufacturing.
You are consolidating planned batch orders for a specific medication. The order must cover two weeks of demand. No other items need to be consolidated.
You need to change the coverage group of the items.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Answer:
Explanation:

NEW QUESTION # 26
A company produces homeopathic lotions for pain relief. The lotions use a combination of ProductA and ProductB. ProductA is the primary ingredient. You use ProductB to adjust the concentration of active ingredients in the lotion.
You need to ensure that the lotion final product has a consistent concentration of anti-inflammatory agents.
Which two actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
- A. Set the formula line type of ProductC to None
- B. Set the formula line type of ProductA to Compensating
- C. Set the formula line type of ProductA to Active
- D. Set the formula line type of ProductB to Active
- E. Set the formula line type of ProductB to Compensating
Answer: C,E
Explanation:
Section: Create, process, and manage production batch orders
Explanation/Reference:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/batch-balancing
NEW QUESTION # 27
You manage pricing for a food processing company. The raw materials used by the business is a commodity-traded product and has a changing purchase price.
You must implement the commodity pricing module. You create a pricing template with margin data.
You need to calculate the cost price for the manufactured goods as well as the sales price based on margin standards.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Answer:
Explanation:
Explanation
NEW QUESTION # 28
A company implements Dynamics 365 for Finance and Operations. You must use functionality in the system for group production runs to prevent downtime and excessive cleaning of the machines on the production line.
You need to set up the system.
Which behaviors should you expect? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
Answer:
Explanation:
Explanation
NEW QUESTION # 29
A company plans to account for indirect costs related to materials used to manufacture products.
The items used to manufacture products have surcharge rates that depend on the type of product being used.
You need to set up the costing sheet to include surcharges for specific items.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Answer:
Explanation:
NEW QUESTION # 30
A process manufacturing company is implementing rebates in Dynamics 365 for Finance and Operations for some of their customers on specific items.
You are the production consultant in charge of implementing the processes needed for calculating and applying the rebates for the subset of customer and items.
You need to implement the order of transactions to process the rebates.
In which order should the actions be performed? To answer, move all actions from the list of actions to the answer area and arrange them in the correct order.
Answer:
Explanation:
Explanation
Reference:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/sales-marketing/tasks/process-customer-rebates
NEW QUESTION # 31
A manufacturing company is implementing Dynamics 365 Supply Cham Management.
Bill of materials (BOMs) must be calculated using standard cost principles.
Miscellaneous charges must be included in the unit cost price. The explosion mode must arways be enforced as single level.
You need to configure the system to meet the requirements.
Which configuration should you enable for each requirement? To answer, drag the appropriate configurations to the correct requirements. Each configuration may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
Answer:
Explanation:
NEW QUESTION # 32
You have updated a cost category price from $5.00 to S7.00. You process a production order which uses the cost category. After ending the order, you realize a new standard cost was not calculated after the price update. You need to validate how this impacted the financial voucher transactions. What transaction would you see in the general ledger?
- A. $2.00 debit to the production quantity variance account
- B. $2.00 credit to the production price variance account
- C. $2.00 credit to the lot size variance account
- D. $2.00 debit to the production price variance account
Answer: B
Explanation:
Reference:
https://docs.microsoft.com/en-us/dynamicsax-2012/appuser-itpro/about-analyzing-common-sources-of-production-variances
NEW QUESTION # 33
A glass bottle manufacturer uses route operations to schedule resources and track manufacturing costs.
The company has recently seen an increase in demand and purchases another resource. The company uses the same costs per resource. However, the new resource costs more to run. The company must be able to track cost contributions for the new resource.
You need to create a cost category for the new resource.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
NOTE: Each correct selection is worth one point.
Answer:
Explanation:
Explanation
NEW QUESTION # 34
A company uses warehouse management and manufacturing execution to process their production orders.
You configure the manufacturing execution production order defaults to always consume Bill of materials (BOM) components when an operation step is completed in the job registration terminal. You create a production order. The order is in released status.
You need to process this order all the way through to end status.
Which four actions should you perform in sequence? To answer, check the appropriate actions to the answer area and arrange them in the correct order.
Answer:
Explanation:
Explanation

NEW QUESTION # 35
......
Dumps for Free MB-320 Practice Exam Questions: https://www.prep4pass.com/MB-320_exam-braindumps.html
PDF Dumps 2023 Exam Questions with Practice Test: https://drive.google.com/open?id=1BhPTSELYIvFqIXnfpPNVX16sQGjEtA5P