NEW QUESTION 47
You want to use subnetworks during the project. Which of the following statements describes subnetworks?

  • A. A subnetwork cannot be defined for a superior subnetwork.
  • B. Subnetworks must be scheduled separately from the superior network.
  • C. The scheduling type of a subnetwork is always copied from the superior network.
  • D. Maintenance orders can be defined as subnetworks.

Answer: D

 

NEW QUESTION 48
You are working with predefined project coding masks to create projects. Which of the following statements apply? Note: There are 2 correct Answers to this question.

  • A. You can use the same coding mask for standard projects and operative projects.
  • B. You can shorten the project mask even when there are existing projects.
  • C. You can only use numbers for a project coding mask definition.
  • D. You can use an indicator to determine that only coded project numbers may be used within SAP Project System.

Answer: A,D

 

NEW QUESTION 49
You want to use billing for a customer project. Which customizing object controls the billing of sales order items?

  • A. Schedule line category
  • B. Requirements type
  • C. Item category
  • D. Requirements class

Answer: C

 

NEW QUESTION 50
You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation? Note: There are 2 correct Answers to this question.

  • A. The material master is set to external procurement.
  • B. The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never".
  • C. The availability check for material components indicates missing parts.
  • D. The material is assigned to the activity as a non-stock material.

Answer: B,C

 

NEW QUESTION 51
What are some of the possible functions in user status profiles? Note: There are 2 correct Answers to this question.

  • A. Ensure user status must always be set manually.
  • B. Restrict setting user status for individual users.
  • C. Allow business processes forbidden by SAP system status.
  • D. Utilize priorities for setting the user status.

Answer: B,D

 

NEW QUESTION 52
Which object is relevant in assembly processing to create an assembly order for the SD document?

  • A. Item category
  • B. Control key
  • C. Requirement class
  • D. Project profile

Answer: C

 

NEW QUESTION 53
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct Answers to this question.

  • A. Material master
  • B. WBS element
  • C. BOM item
  • D. Network activity

Answer: C,D

 

NEW QUESTION 54
Where can you assign the user status profile for WBS elements? Note: There are 3 correct Answers to this question.

  • A. In the project version
  • B. In the project definition of a standard WBS
  • C. In the project type
  • D. In the operative WBS element
  • E. In the project profile

Answer: B,D,E

 

NEW QUESTION 55
You want to allocate overhead rates to a WBS element. What must you assign to the WBS element?

  • A. Settlement rule
  • B. Investment profile
  • C. Costing sheet
  • D. Results analysis key

Answer: C

 

NEW QUESTION 56
Which of the following statements apply to project versions? Note: There are 2 correct Answers to this question.

  • A. Project versions can be created automatically based on user status.
  • B. Manually created project versions always require a project version profile.
  • C. Project versions are mandatory for Milestone Trend Analysis (MTA).
  • D. Project versions can be changed.

Answer: C,D

 

NEW QUESTION 57
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct Answers to this question.

  • A. Shift activities backward or forward on the time axis where more capacities are available.
  • B. Maintain subordinate internal activity elements assigned to other work centers.
  • C. Increase the capacities of the work center in the project planning board.
  • D. Trigger automatic capacity leveling inside the project planning board.

Answer: A,D

 

NEW QUESTION 58
Which of the following factors influence the scheduling of internal processing activities? Note: There are
3 correct Answers to this question.

  • A. Whether the work for the internal activity is greater than its duration
  • B. The unit (for example, hour, day) of the field Normal Duration field of the activity
  • C. The relationships between activity elements
  • D. The factory calendar in the work center used for the internal processing activity
  • E. An activated Scheduling indicator in the control key of the internal processing activity

Answer: C,D,E

 

NEW QUESTION 59
What are valid procurement types for stock items? Note: There are 3 correct Answers to this question.

  • A. Preliminary purchase requisition for WBS element
  • B. Purchase requisition and Reservation for WBS element
  • C. Planned order
  • D. Third-party order
  • E. Reservation for WBS element

Answer: A,B,E

 

NEW QUESTION 60
Which objects can be used to specify settlement rules? Note: There are 2 correct Answers to this question.

  • A. Network header for activity-account-assigned networks
  • B. WBS elements
  • C. Standard WBS elements
  • D. Network activity for activity-account-assigned networks

Answer: A,B

 

NEW QUESTION 61
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?

  • A. Network profile
  • B. Data entry profile
  • C. Network type
  • D. Project profile

Answer: B

 

NEW QUESTION 62
Which of the following business processes do NOT lead to the booking of actual costs to an object?
Note: There are 2 correct Answers to this question.

  • A. Goods receipt of a non-stock item
  • B. Goods receipt into unvaluated project stock
  • C. Goods receipt into valuated project stock
  • D. Recording of external services in the service entry sheet

Answer: B,D

 

NEW QUESTION 63
Where do you maintain the length of the project ID?

  • A. Project coding mask
  • B. Special characters
  • C. Project type
  • D. Project profile

Answer: A

 

NEW QUESTION 64
Where do you control whether a project stock is managed as valuated or non-valuated project stock?

  • A. In the project definition
  • B. In the material master
  • C. In the network activity
  • D. In the WBS element

Answer: A

 

NEW QUESTION 65
Which organizational structures are required for network activities? Note: There are 3 correct Answers to this question.

  • A. Company code
  • B. Sales organization
  • C. Operating concern
  • D. Plant
  • E. Controlling area

Answer: A,D,E

 

NEW QUESTION 66
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?

  • A. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element.
  • B. Activate availability control for the WBS elements. Define the tolerance limits on each WBS element.
  • C. Activate commitment management in the project definition. Enter the budget in the master data of the top WBS element.
  • D. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing.

Answer: D

 

NEW QUESTION 67
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct Answers to this question.

  • A. The network is assigned to a sales order item.
  • B. The network activity is assigned to a WBS element.
  • C. The Project Stock indicator is set in the project definition (non-valuated or valuated).
  • D. The material master of the component must permit project stock management.
  • E. A procurement indicator must be assigned to the activity.

Answer: C,D,E

 

NEW QUESTION 68
Which of the following apply to dynamic item processor (DIP)? Note: There are 3 correct Answers to this question.

  • A. DIP is used to create a quotation.
  • B. Material determination is mandatory.
  • C. Sales prices are maintained in the DIP profile.
  • D. Usage of cost elements is mandatory.
  • E. Sources can be based on line items.

Answer: A,C,E

 

NEW QUESTION 69
......